  • SSI DECM EVMS Tests

SSI DECM EVMS Tests

SSI EVMS DECM Tests
 
Metric ID
Description
SSI Inspection Method
Metric Threshold
Project Archive required
DECM Test Spec
SSI Test Method
05A101a
Does each control account have exactly one responsible organizational element assigned?
Inspect Schedule items with a Control Account (CA).  Find condition where the OBS for a CA is missing.  Find condition where the WPs in a CA have no OBS or the OBS for WPs is not the same as the OBS of the CA. The Schedule will pass this test if 0 conditions are found.
X = 0
No
05A102a
Is each control account assigned to a single Control Account Manager (CAM)?
Inspect Schedule items with a Control Account (CA).  Find condition where the CAM for a CA is missing.  Find condition where the WPs in a CA have no CAM or the CA for WPs does not match the CAM of the CA. The Schedule will pass this test if <5% of CAs have this condition.
X/Y <= 5%
No
05A103a
Does each control account have exactly one WBS element assigned?
Inspect Schedule items with a Control Account (CA).  Find condition where the WBS for a CA is missing.  Find condition where the WPs in a CA have no WBS or the WBS for WPs does not rollup to the WBS of the CA. The Schedule will pass this test if 0 conditions are found.
X = 0
No
09A103a
Are elements of cost defined/identified for each control account?
Determines if Elements of Cost (EOC) are identified & segregated for incomplete Control Accounts (CAs).  Sum the Baseline work and cost for incomplete CAs as the Denominator.  Then sum the Baseline work and cost for incomplete CAs containing Work Packages or Planning Packages with mixed or no EOC identified.
X/Y <= 10%
No
10A102a
Are EVTs assigned to WPs?
Work Packages missing EVT/PMT
X/Y <= 5%
No
10A103a
Are 0-100 EVTs applied to incomplete WPs with one accounting period of budget?
Baseline POP in one period w/o 0/100
X/Y <= 5%
No
10A104a
Are %Start-%Finish EVTs applied to incomplete WPs with two accounting periods of budget?
Baseline POP in two period w/o X/Y
X/Y <= 5%
No
10A105a
Is BCWP claimed consistent with the WP EVT?
SSI identifies incomplete 0/100, non-LOE Work Packages (WPs) with Physical % Complete >0, non-LOE WPs with no Actual Start date with Physical % Complete >0.  Additionally, if the % Start value for X/Y EV Types can be determined, SSI Tools will evaluate the consistent of those as well.
X/Y <= 5%
No
10A109b
Does each WP/PP have an assigned budget?
WP/PP without assignments
X/Y <= 5%
No
10A202a
Is material segregated from other elements of cost within work packages?
Identifies Work Packages (WPs) with material and non material assignment Element of Cost (EOC)
X = 0
No
10A302b
Have PPs earned performance?  
Open PPs in IMS
 X/Y <= 2%
No
10A303a
Do all PPs have duration?
PPs with 0 duration
X/Y <= 10%
No
11A101a
Does the BAC value for all CAs equate to the sum of their WP and PP budgets?
NOTE - SSI Method is different than DECM since the DECM method would produce the same value for the numerator and denominator in a schedule.  SSI Summarizes the baseline work and cost (BAC) for all items in the schedule with a Control Account (CA).  This is the the Denominator in the report.  Then it sums the BAC for all Work Packages (WP) as the Numerator.  If these numbers are different, the schedule has items with a CA but no WP or vice versa.
X/Y <= 1%
No
12A201a
Are LOE WPs separately evaluated from discrete WPs within the same control account?
Identifies Work Packages (WPs) with a mixture of tasks that are LOE and tasks that are not LOE.
X/Y <= 10%
No
12I101a
Do LOE WPs have schedule variances?  
Identifies LOE Work Packages with Start or Finish Variances from the Baseline
X = 0
No
29A401a
Are there changes to open WPs?
NOTE - SSI Method is different than DECM due to lack of burdened cost data in IMS.  Report all open work packages with a different baseline work or cost value in the prior period.
X/Y <= 5%
Requires Current Project plus 1 prior reporting period
29A601a
Is all effort detailed planned within the current rolling wave?
Report of Planning Packages with a Start date before the start of the next rolling wave
X/Y <= 10%
No
29I401a
Are baseline dates being updated to mask legitimate variances?
No Pass/Fail is determined by SSI Tools since baseline changes may have been the result of baseline change control log entries with acceptable substantiation.  Report of WPs in the last 3 reporting periods with different Baseline Start and Finish dates from period to period.
X/Y <= 10%
Requires Current Project plus 2 prior reporting periods