SSITools13-4-1_Ribbon
Trace Driving Path Show All Tasks Button Schedule Health/Audits Post Task Status Open Watchlist Tools Adjust Task End Date Project Performance Report Find on Excel Sheet Open Toolbox Get Time Scaled Values SRA Sensitivity Analysis Cobra & MPM Bridge Tools EV Performance Reports Integrate Distribute Link Inputs/Outputs Identify Input/Output Identify Sub-Project Sync Remote Projects Open Example Project SSI Tools Help Check for Updates

Show All Tasks Button

Click this button to clear all sorting, filters, and groups and expand all levels of the Work Breakdown Structure.

Post Task Status

Ensure valid status of tasks with SSI’s Post Task Status form.  Invalid dates (projected dates before or actual dates after the current project status date) are shown in yellow to remind you to address their status. 

Open Watchlist Tools

The SSI Watchlist is useful for tracking variances on key items in one section of a schedule as you are working in another section of a schedule. Each time you make a change in the schedule that has the potential to cause a variance to the key milestones, you can click Check for Variances to see if any of your changes has caused a schedule variance relative to the dates you are tracking.

Adjust Task End Date

Pick a date from a simple calendar pop-up and have SSI Tools calculate how much to increase or decrease a task’s duration to reach that date – without adding date constraints.

Find on Excel Sheet

Open Toolbox

Get Time Scaled Values

SRA Sensitivity Analysis

Cobra & MPM Bridge Tools

Open Example Project

SSI Tools is packaged with an example project that you can use as a playground to try out and learn all of your SSI Tools.

Check for Updates

Check to make sure you are always on the latest version of SSI Tools by checking for updates. Set update preferences, and be notified of new updates automatically.