EV Performance Tools

 
Suggest Earned Value Technique (EVT) According to Accounting Periods
Use this form to add a suggested Earned Value Technique (EVT) for Work Packages according to their baseline period of performance.  This feature identifies all tasks in a project with the same Work Package ID and determines how its Duration, Work or Cost are spread over accounting periods per the calendar you specify on the tab named Project Fields for EV.  Suggested EVT is written to a project text or outline code field.
 
Set Physical % Complete according to Earned Value Technique
This feature corrects or sets Physical % Complete according to the user's selections.  If the EVT can be determined by the user's codes and conventions, the option named If In Progress, set Physical % Complete per X/Y EV Technique will set Physical % Complete equal to the X value of a X/Y EVT.
 
 
 
 