SSIEV1202 - For those needing to use a formal Earned Value Management System, SSI Tools includes a “bridge” from Microsoft Project to Deltek Cobra. SSI’s Cobra Bridge Tools make import / transaction files that include WBS, Planned Value, Earned Value, and Estimates to Complete.
SSIEV1203 - Instructions on setting up a new project in Deltek Cobra including a project Calendar, Code files, Rate files and Resource tables. Once the Cobra Project is established, you can use SSI’s “Bridge” to Cobra to generate import files from Microsoft Project containing BCWS, BCWP, BAC and ETC to ensure consistency between your project tasks (as work packages, planning packages) and their corresponding data in the Deltek Cobra project file.
Select End of Cycle Tools / Cobra Bridge Tools in the Performance and Earned Value group: